Project risk management for community-based post-disaster housing reconstruction

Ophiyandri, T

Authors

T Ophiyandri



Abstract

Indonesia is a country that is highly susceptible to disasters, particularly earthquakes. In the last decade, Indonesia has been hit by three large earthquakes; Aceh in December 2004, Yogyakarta in May 2006, and West Sumatra in September 2009. These earthquakes have created considerable losses to Indonesian communities, leading to 130,000 fatalities, US$10.3 billions in economic losses, and 500,000 heavily damaged houses. The extensiveness of housing reconstruction is the most problematic issue in the housing reconstruction programme sector. Although a community-based post-disaster housing reconstruction project (CPHRP) has been implemented, nevertheless the outcome was overshadowed by delays in delivery, cost escalation, unexpected quality, and community dissatisfaction. The implementation of good practice in project risk management in the construction industry is expected to enhance the success of CPHRP. Accordingly, this study aims to develop a risk management model for community-based post-disaster housing reconstruction approach.

In order to achieve the aim and objective of the research, multiple case studies are selected as research strategies. This study implements the sequential mixed method application, starting with a semi-structured interview and followed by a questionnaire survey as the primary method. Content analysis was used to analyse qualitative data, whilst descriptive and inferential statistics were deployed to analyse quantitative data.

The novelty of the research is as follows: this study reveals the importance of the understanding of a community-based approach in post-disaster housing reconstruction. Four highly significant advantages of CPHRP have been discovered, the most significant advantage being that it ‘creates a sense of ownership’ to beneficiaries of the project. The psychological advantage of CPHRP was also found to be greater than the construction advantage. Furthermore, the risk assessment revealed some high-risk events during the pre-construction stage of CPHRP. The project objective most affected by them is project time completion. A risk response document has also been proposed. Moreover, this study found twelve critical success factors (CSFs) of CPHRP, with the highest of the CSFs being ‘transparency and accountability’. With careful attention paid to the above findings, it is expected that the success of the implementation of CPHRP can be increased.

Citation

Ophiyandri, T. Project risk management for community-based post-disaster housing reconstruction. (Thesis). University of Salford

Thesis Type Thesis
Deposit Date Mar 7, 2014
Publicly Available Date Mar 7, 2014
Additional Information Funders : Ministry of National Education and Culture, Republic of Indonesia