I Ndekugri
Delay analysis within construction contracting organizations
Ndekugri, I; Braimah, N; Gameson, RN
Authors
N Braimah
RN Gameson
Abstract
Delayed completion of a construction project is often caused by a complex interaction of a combination of events, some of which are the contractor’s risks and others are the project owner’s. The apportionment of the liability to give effect to the risk allocation has therefore been a matter of great controversy. Many delay analysis methodologies have been developed over the years for performing this task. This paper reports on an empirical study into the current practice in the use of these methodologies in the United Kingdom, as part of a wider study aimed at developing a framework for improving delay claims analysis. The part of the study reported here was based on a questionnaire survey of key informants. The issues investigated include the categories of staff within contracting organizations who contribute to delay claims analyses, the awareness, use and reliability of existing delay analysis methods and the obstacles to their use in
practice. The main findings of the study are that: (1) the preparation of delay claims often requires input from commercial managers (quantity surveyors), schedulers, site managers, external claim consultants and estimators;(2) commercial managers have the greatest involvement; (3) claims analyzed using the as-built versus as-planned and the impacted as-planned techniques are often successful
although there is considerable literature on the shortcomings of these techniques; and (4)the main obstacles to the use of the methods relates to deficiencies in project records and scheduling practice.
Citation
Ndekugri, I., Braimah, N., & Gameson, R. (2008). Delay analysis within construction contracting organizations. Journal of Construction Engineering and Management, 134(9), 692-700. https://doi.org/10.1061/%28ASCE%290733-9364%282008%29134%3A9%28692%29
Journal Article Type | Article |
---|---|
Publication Date | Sep 1, 2008 |
Deposit Date | Feb 24, 2013 |
Journal | Journal of Construction Engineering and Management |
Print ISSN | 0733-9364 |
Publisher | Coasts, Oceans, Ports and Rivers Institute |
Peer Reviewed | Peer Reviewed |
Volume | 134 |
Issue | 9 |
Pages | 692-700 |
DOI | https://doi.org/10.1061/%28ASCE%290733-9364%282008%29134%3A9%28692%29 |
Keywords | Claims; Delay time; Construction management; Damage; Scheduling. |
Publisher URL | http://dx.doi.org/10.1061/(ASCE)0733-9364(2008)134:9(692) |
Related Public URLs | http://ascelibrary.org/journal/jcemd4 |
Downloadable Citations
About USIR
Administrator e-mail: library-research@salford.ac.uk
This application uses the following open-source libraries:
SheetJS Community Edition
Apache License Version 2.0 (http://www.apache.org/licenses/)
PDF.js
Apache License Version 2.0 (http://www.apache.org/licenses/)
Font Awesome
SIL OFL 1.1 (http://scripts.sil.org/OFL)
MIT License (http://opensource.org/licenses/mit-license.html)
CC BY 3.0 ( http://creativecommons.org/licenses/by/3.0/)
Powered by Worktribe © 2024
Advanced Search